[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119742":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119742,789,1,"单选题","某建设工程承包采用固定单价合同，地基与基础分部工程施工历时1年，通货膨胀率8%，完成后，其钢筋混凝土工程实际完成的工程量是2016m3，而投标时工程量清单中该分项的工程量是2000m3。在这种情况下，业主应根据（）计算该分项应付的工程款。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","2000m3乘以合同单价",false,{"key":16,"text":17,"correct":14},"B","2000m3乘以调整后的单价",{"key":19,"text":20,"correct":21},"C","2016m3乘以合同单价",true,{"key":23,"text":24,"correct":14},"D","2016m3乘以调整后的单价","2021\u002F2020教材P253页 固定单价合同（价格不可调）和变动单价合同（通货膨胀达到一定水平或者国家政策发生变化时）的合同价格确定问题，原文是“固定单价合同条件下，无论发生哪些影响价格的因素都不对单价进行调整”和“实际工程款的支付也将以实际完成工程量乘以合同单价进行计算”。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]