[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119741":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119741,789,1,"单选题","下列关于固定总价合同适用性说法不正确的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程量小、工期短，施工过程中环境因素变化小，工程条件稳定并合理",false,{"key":16,"text":17,"correct":14},"B","工程设计详细，图纸完整、清楚，工程任务和范围明确",{"key":19,"text":20,"correct":14},"C","工程结构和技术简单，风险小",{"key":22,"text":23,"correct":24},"D","合同条件中有对承包商单方面保护的条款",true,"2021\u002F2020教材P254页 （5）合同条件中双方的权利和义务十分清楚，合同条件完备。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]