[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119739":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119739,789,1,"单选题","某按单价合同计价的招标工程，在评标过程中，发现某投标人的总价与单价的计算结果不一致，究其原因是投标人在计算时，将混凝土单价300元／m3误作为30元／m3的结果。对此，业主有权（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","以总价为准调整单价",false,{"key":16,"text":17,"correct":18},"B","以单价为准调整总价",true,{"key":20,"text":21,"correct":14},"C","将该投标文件作废标处理",{"key":23,"text":24,"correct":14},"D","要求投标者重新提报混凝土单价","2021\u002F2020教材P252页 对于投标书中明显的数字计算错误，业主有权力先作修改再评标，当总价和单价的计算结果不一致，以单价为准调整总价。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]