[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119738":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119738,789,1,"单选题","成套设备安装后的试车检验不合格，下列说法正确的是( )。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","若属于设备质量的原因，由供货方负责修理、更换，由安装方承担全部费用",false,{"key":16,"text":17,"correct":18},"B","若属于设备质量的原因，由供货方负责修理、更换，并承担全部费用",true,{"key":20,"text":21,"correct":14},"C","若由于工程施工质量问题，由供货方负责拆除后纠正缺陷",{"key":23,"text":24,"correct":14},"D","若由于工程施工质量问题，由施工方负责拆除后纠正缺陷","2021\u002F2020教材P252页 若检验不合格，属于设备质量原因，由供货方负责修理、更换并承担全部费用；如果由于工程施工质量问题，由安装单位负责拆除后纠正缺陷。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]