[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119735":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119735,789,1,"单选题","设备制造前，业主应支付设备价格的（）作为预付款。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","20%",false,{"key":16,"text":17,"correct":14},"B","15%",{"key":19,"text":20,"correct":21},"C","10%",true,{"key":23,"text":24,"correct":14},"D","8%","2021\u002F2020教材P251页 合同价款的支付一般分三次：①设备制造前，采购方支付设备价格的10%作为预付款；②供货方按照交货顺序在规定的时间内将货物送达交货地点，采购方支付该批设备价的80%；③剩余的10%作为设备保证金，待保证期满，采购方签发最终验收证书后支付。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]