[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119730":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119730,789,1,"单选题","物资采购合同中应该明确所采用的计量方法与计量单位，对于没有国家、行业或地方规定的计量标准的产品，计量单位应采用()的计量标准。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","供货单位",false,{"key":16,"text":17,"correct":14},"B","采购单位",{"key":19,"text":20,"correct":14},"C","行业惯例",{"key":22,"text":23,"correct":24},"D","当事人协商",true,"2021\u002F2020教材P249页 合同中应该明确所采用的计量方法，并明确计量单位。凡国家、行业或地方规定有计量标准的产品，合同中应按照统一标准注明计量单位，没有规定的，可由当事人协商执行，不可以用含混不清的计量单位。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]