[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119724":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119724,789,1,"单选题","《建筑工程施工劳务分包合同(示范文本)》中规定，从工程承包人收到劳务发包人递交的结算资料到工程承包人向劳务分包人支付劳务报酬尾款，最长不得超过( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","7天",false,{"key":16,"text":17,"correct":14},"B","14天",{"key":19,"text":20,"correct":21},"C","28天",true,{"key":23,"text":24,"correct":14},"D","30天","2021\u002F2020教材P248页 2.工程承包人收到劳务分包人递交的结算资料后14天内进行核实，给予确认或者提出修改意见。工程承包人确认结算资料后14天内向劳务分包人支付劳务报酬尾款。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]