[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119722":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119722,789,1,"单选题","按照《建筑工程施工劳务分包合同（示范文本）》，下列由劳务报酬最终支付程序规定的表述中，正确的是( )",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","全部工作完成，经工程承包人确认后7天内，劳务分包人向工程承包人递交完整的结算资料",false,{"key":16,"text":17,"correct":14},"B","全部工作完成，经承包人认可后28天内，劳务分包人向工程承包人递交完整的结算资料",{"key":19,"text":20,"correct":14},"C","工程承包人收到劳务分包人递交的结算资料后28天内进行核实，给予确认或者提出修改意见",{"key":22,"text":23,"correct":24},"D","工程承包人确认结算资料后14天内向劳务分包人支付劳务报酬尾款",true,"2021\u002F2020教材P248页 1.全部工作完成，经工程承包人认可后14天内，劳务分包人向工程承包人递交完整的结算资料，双方按照本合同约定的计价方式，进行劳务报酬的最终支付。2 工程承包人收到劳务分包人递交的结算资料后14天内进行核实，给予确认或者提出修改意见。工程承包人确认结算资料后14天内向劳务分包人支付劳务报酬尾款。3 劳务分包人和工程承包人对劳务报酬结算价款发生争议时，按合同约定处理。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]