[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119721":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119721,789,1,"单选题","根据《建设工程施工劳务分包合同（示范文本）》（GF2003—0214），运至施工场地用于劳务施工的材料和待安装设备应由（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程承包人办理并支付保险费用",true,{"key":16,"text":17,"correct":18},"B","劳务分包人办理并支付保险费用",false,{"key":20,"text":21,"correct":18},"C","工程承包人办理，但由劳务分包人支付保险费用",{"key":23,"text":24,"correct":18},"D","劳务分包人办理，但由承包人支付保险费用","2021\u002F2020教材P247页 运至施工场地用于劳务施工的材料和待安装设备，由工程承包人办理或获得保险，且不需劳务分包人支付费用。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]