[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119710":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119710,789,1,"单选题","根据《建设工程专业工程分包合同（示范文本）》规定，分包合同价款与总包合同相应部分款之间应当（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","一致",false,{"key":16,"text":17,"correct":18},"B","没有连带关系",true,{"key":20,"text":21,"correct":14},"C","分包价款低于总包价款",{"key":23,"text":24,"correct":14},"D","分包价款高于总包价款","2021\u002F2020教材P246页 合同价款及支付2.分包合同价款与总包合同相应部分价款无任何连带关系。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]