[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119699":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119699,789,1,"单选题","某项目业主作为采购方与钢材生产厂家签订了物资采购合同，合同中规定供货方负责将钢材送达采购方制定地点，由采购方人员对到达的钢材进行检查，发现问题当场作出记录。本合同中，双方约定的验收方式是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","驻厂验收",false,{"key":16,"text":17,"correct":14},"B","提运验收",{"key":19,"text":20,"correct":21},"C","接运验收",true,{"key":23,"text":24,"correct":14},"D","入库验收","2021\u002F2020教材P250页 接运验收：由接运人员对到达的物资进行检查，发现问题当场作出记录。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]