[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119697":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119697,789,1,"单选题","某建筑材料采购合同中约定由需方负责提货，则交货日期应是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","以需方收货戳记的日期为准",false,{"key":16,"text":17,"correct":18},"B","以供方按合同规定通知的提货日期为准",true,{"key":20,"text":21,"correct":14},"C","以承运单位签发的日期为准",{"key":23,"text":24,"correct":14},"D","以供方向承运单位提出申请的日期为准","2021\u002F2020教材P250页 交货日期的确定可以按照下列方式：(1)供货方负责送货的，以采购方收货戳记的日期为准；(2)采购方提货的，以供货方按合同规定通知的提货日期为准；(3)凡委托运输部门或单位运输、送货或代运的产品，一般以供货方发运产品时承运单位签发的日期为准，不是以向承运单位提出申请的日期为准。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]