[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119695":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119695,789,1,"单选题","根据《建设工程施工劳务分包合同（示范文本）》(GF-20030214)规定，采用()的，由劳务分包人每日将提供劳务人数报工程承包人，由工程承包人确认。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","固定劳务报酬方式",false,{"key":16,"text":17,"correct":18},"B","按确定的工时计算劳务报酬",true,{"key":20,"text":21,"correct":14},"C","按确定的工程量或工时计算劳务报酬",{"key":23,"text":24,"correct":14},"D","按确定的工程量计算劳务报酬","2021\u002F2020教材P248页 采用按确定的工时计算劳务报酬的，由劳务分包人每日将提供劳务人数报工程承包人，由工程承包人确定。采用固定劳务报酬方式的，施工过程中不计算工时和工程量。采用按确认的工程量计算劳务报酬的，由劳务分包人按月或旬，日，将完成的工程量报工程承包人，由工程承包人确认。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]