[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119692":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119692,789,1,"单选题","组建与工程相适应的项目管理班子，全面履行总（分）包合同，组织实施施工管理的各项工作，对工程的工期和质量向()负责。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","分包人",false,{"key":16,"text":17,"correct":14},"B","总承包人",{"key":19,"text":20,"correct":21},"C","发包人",true,{"key":23,"text":24,"correct":14},"D","监理人","2021\u002F2020教材P246页 对劳务分包合同条款中规定的工程承包人的主要义务归纳如下。1.组建与工程相适应的项目管理班子，全面履行总（分）包合同，组织实施施工管理的各项工作，对工程的工期和质量向发包人负责；",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]