[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119683":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119683,789,1,"单选题","根据《标准施工招标文件》中“通用合同条款的规定”，承包人的缺陷责任期应自()起计算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人提交竣工验收申请报告之日",false,{"key":16,"text":17,"correct":18},"B","工程接收证书中写明的实际竣工日期",true,{"key":20,"text":21,"correct":14},"C","发包人签认工程接收证书之日",{"key":23,"text":24,"correct":14},"D","监理人向承包人出具经发包人签认的工程接收证书之日","2021\u002F2020教材P243页 缺陷责任期自实际竣工日期起计算。在全部工程竣工验收前，已经发包人提前验收的单位工程，其缺陷责任期的起算日期相应提前。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]