[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119682":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119682,789,1,"单选题","缺陷责任期自()日期起计算。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","计划开工",false,{"key":16,"text":17,"correct":14},"B","实际开工",{"key":19,"text":20,"correct":21},"C","实际竣工",true,{"key":23,"text":24,"correct":14},"D","计划竣工","2021\u002F2020教材P243页 缺陷责任期缺陷责任期自实际竣工日期起计算。在全部工程竣验收前，已经发包人提前验收的单位工程，其缺陷责任期的起算日期相应提前。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]