[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119681":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119681,789,1,"单选题","合同工程尚未全部竣工，其中某项或某几项单位工程或工程设备安装已竣工，根据专用条款约定，需要投入施工期运行的，经（）约定验收合格，证明能确保安全后，才能在施工期投入运行。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理人",false,{"key":16,"text":17,"correct":18},"B","发包人",true,{"key":20,"text":21,"correct":14},"C","监理人与承包人",{"key":23,"text":24,"correct":14},"D","发包人与承包人","2021\u002F2020教材P243页 施工期运行是指合同工程尚未全部竣工，其中某项或某几项单位工程或工程设备安装已竣工，根据专用合同条款约定，需要投入施工期运行的，经发包人约定验收合格，证明能确保安全后，才能在施工期投入运行。在施工期运行中发现工程或工程设备损坏或存在缺陷的，由承包人按合同规定进行修复。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]