[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119679":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119679,789,1,"单选题","根据《标准施工招标文件》，发包人应在收到承包人提交竣工结算款支付申请后()天内予以核实，向承包人签发竣工结算支付证书；发包人签发竣工结算支付证书后的()天内，按照竣工结算支付证书列明的金额向承包人支付结算款。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7，14",false,{"key":16,"text":17,"correct":18},"B","14,14",true,{"key":20,"text":21,"correct":14},"C","28,28",{"key":23,"text":24,"correct":14},"D","56，28","2021\u002F2020教材P241页 发包人应在收到后14天内审核完毕，由监理人向承包人出具经发包人签认的最终结清证书。发包人应在监理人出具最终结清证书后的14天内，将应支付款支付给承包人。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]