[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119678":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119678,789,1,"单选题","发包人应在监理人收到进度付款申请单后的()天内，将进度应付款支付给承包人。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","30",false,{"key":16,"text":17,"correct":14},"B","7",{"key":19,"text":20,"correct":21},"C","28",true,{"key":23,"text":24,"correct":14},"D","15","2021\u002F2020教材P240页 发包人应在监理人收到进度付款申请单后的28天内，将进度应付款支付给承包人。发包人不按期支付的，按专用合同条款的约定支付逾期付款违约金。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]