[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119675":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119675,789,1,"单选题","某工程项目承包人于2006年5月1日按合同规定向监理人报送竣工验收申请报告，但直到2006年7月中旬，发包人无故一直没有组织竣工验收，则根据《标准施工招标文件》中“通用合同条款”的规定应()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","由承包人继续承担工程保管责任",false,{"key":16,"text":17,"correct":14},"B","由承包人自行组织竣工验收",{"key":19,"text":20,"correct":14},"C","视为验收合格，实际竣工日期以收到承包人竣工验收申请报告后的第56天为准",{"key":22,"text":23,"correct":24},"D","视为验收合格，实际竣工日期以承包人提交竣工验收申请报告的日期为准",true,"2021\u002F2020教材P242页 发包人在收到承包人竣工验收申请报告56天后未进行验收的，视为验收合格，实际竣工日期以提交竣工验收申请报告的日期为准，但发包人由于不可抗力不能进行验收的除外。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]