[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119672":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119672,789,1,"单选题","一般情况下，验收合格工程的实际竣工日期是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","组织工程竣工验收的日期",false,{"key":16,"text":17,"correct":14},"B","承包人实际完成工程的日期",{"key":19,"text":20,"correct":21},"C","承包人提交竣工验收申请报告的日期",true,{"key":23,"text":24,"correct":14},"D","工程竣工验收后，发包人给予认可意见的日期","2021\u002F2020教材P242页 3.验收。（6）发包人在收到承包人竣工验收申请报告56天后未进行验收的，视为验收合格，实际竣工日期以提交竣工验收申请报告的日期为准，但发包人由于不可抗力不能进行验收的除外。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]