[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119667":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119667,789,1,"单选题","根据《标准施工招标文件》中“通用合同条款”的规定，如监理人未能在14天内核查承包人提交的竣工付款申请单，又未提出具体意见，则()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","监理人可要求延长核查时间",false,{"key":16,"text":17,"correct":14},"B","监理人应向承包人出具经发包人签认的竣工付款证书",{"key":19,"text":20,"correct":21},"C","视为承包人提交的竣工付款申请已经监理人核查同意",true,{"key":23,"text":24,"correct":14},"D","视为承包人提交的竣工付款申请已经发包人核查同意","2021\u002F2020教材P241页 监理人在收到承包人提交的竣工付款申请单后的14天内完成核查，提出发包人到期应支付给承包人的价款送发包人审核并抄送承包人。发包人应在收到后14天内审核完毕，由监理人向承包人出具经发包人签认的竣工付款证书。监理人未在约定时间内核查，又未提出具体意见的，视为承包人提交的竣工付款申请单已经监理人核查同意。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]