[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119666":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119666,789,1,"单选题","根据《建设工程施工合同（示范文本）》(GF2013-0201)，在监理人出具竣工付款证书后的（）日内，发包人需将应支付款支付给承包人。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","28",{"key":23,"text":24,"correct":14},"D","42","2021\u002F2020教材P241页 监理人在收到承包人提交的竣工付款申请单后的14d内完成核查，提出发包人到期应支付给承包人的价款送发包人审核并抄送承包人。发包人应在收到后14d内审核完毕，由监理人向承包人出具经发包人签认的竣工付款证书。发包人应在监理人出具竣工付款证书后的14d内，将应支付款支付给承包人。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]