[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119665":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119665,789,1,"单选题","根据《标准施工招标文件》中“通用合同条款”的规定，承包人提交竣工付款申请单和最终结清申请单的时间条件分别是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程接收证书颁发后、缺陷责任期终止证书签发后",true,{"key":16,"text":17,"correct":18},"B","工程接收证书颁发后、履约证书签发后",false,{"key":20,"text":21,"correct":18},"C","工程竣工证书颁发后、履约证书签发后",{"key":23,"text":24,"correct":18},"D","工程竣工证书颁发后、缺陷责任期终止证书签发后","2021\u002F2020教材P241页 工程接收证书颁发后，承包人应按专用合同条款约定的份数和期限向监理人提交竣工付款申请单，并提供相关证明材料。缺陷责任期终止证书签发后，承包人可按专用合同条款约定的份数和期限向监理人提交最终结清申请单，并提供相关证明材料。@##",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]