[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119660":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119660,789,1,"单选题","根据《标准施工招标文件》中“通用合同条款”的规定，质量保证金的计算额度应包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预付款的支付",false,{"key":16,"text":17,"correct":18},"B","承包人完成的安装工程款",true,{"key":20,"text":21,"correct":14},"C","价格调整的金额",{"key":23,"text":24,"correct":14},"D","预付款的扣回","2021\u002F2020教材P240页 监理人应从第一个付款周期开始，在发包人的进度付款中，按专用合同条款的约定扣留质量保证金，直至扣留的质量保证金总额达到专用合同条款约定的金额或比例为止。质量保证金的计算额度不包括预付款的支付、扣回以及价格调整的金额。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]