[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119659":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119659,789,1,"单选题","承包人按照监理人批准的计划组织施工，但由于进度计划本身存在缺陷造成工期延误，则责任应由( )承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":18},"B","承包人",true,{"key":20,"text":21,"correct":14},"C","监理人",{"key":23,"text":24,"correct":14},"D","分包人","2021\u002F2020教材P237页 由于承包人原因，未能按合同进度计划完成工作，或监理人认为承包人施工进度不能满足合同工期要求的，承包人应采取措施加快进度，并承担加快进度所增加的费用。本题中进度计划本身存在缺陷造成工期延误是由于承包人原因造成的，因此应由承包人承担责任。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]