[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119658":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119658,789,1,"单选题","发包人要求承包人提前竣工，或承包人提出提前竣工的建议能够给发包人带来效益的，应由（）采取加快工程进度的措施和修订合同进度计划。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","承包人",false,{"key":16,"text":17,"correct":14},"B","发包人",{"key":19,"text":20,"correct":14},"C","发包人与承包人共同协商",{"key":22,"text":23,"correct":24},"D","监理人与承包人共同协商",true,"2021\u002F2020教材P237页 发包人要求承包人提前竣工，或承包人提出提前竣工的建议能够给发包人带来效益的，应由监理人与承包人共同协商采取加快工程进度的措施和修订合同进度计划。发包人应承担承包人由此增加的费用，并向承包人支付专用合同条款约定的相应奖金。承包人应协助发包人办理上述手续。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]