[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119656":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119656,789,1,"单选题","由于发包人的原因发生暂停施工的紧急情况，且监理人未及时下达暂停施工指示的，承包人可先暂停施工并及时向监理人提出暂停施工的书面请求。监理人应在接到书面请求后的（）h内予以答复，未答复的，视为同意承包人的暂停施工请求。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","6",false,{"key":16,"text":17,"correct":14},"B","8",{"key":19,"text":20,"correct":14},"C","12",{"key":22,"text":23,"correct":24},"D","24",true,"2021\u002F2020教材P237页 （3）监理人暂停施工指示②监理人应在接到书面通知后的24h内予以答复，逾期未答复的，视为同意承包人的暂停施工请求。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]