[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119655":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119655,789,1,"单选题","根据《标准施工招标文件》中“通用合同条款”的规定，出现合同专用条款规定的异常恶劣气候条件导致工期延误，则()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人有权要求发包人延长工期",true,{"key":16,"text":17,"correct":18},"B","承包人无权要求发包人延长工期",false,{"key":20,"text":21,"correct":18},"C","承包人有权要求发包人延长工期，并承担有关费用",{"key":23,"text":24,"correct":18},"D","承包人无权要求发包人延长工期，并承担有关费用和合理利润","2021\u002F2020教材P237页 (2)异常恶劣的气候条件：由于出现专用合同条款规定的异常恶劣气候的条件导致工期延误的，承包人有权要求发包人延长工期。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]