[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119654":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119654,789,1,"单选题","根据《标准施工招标文件》中“通用合同条款”的规定，承包人在自检确认隐蔽部位具备覆盖条件后，通知监理人在约定的期限内进行检查。该部分隐蔽工程施工完成后，监理人有权提出对已经隐蔽的工程进行重新检验的要求，则重新检验的费用()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","应由承包人承担",false,{"key":16,"text":17,"correct":14},"B","应由发包人承担",{"key":19,"text":20,"correct":21},"C","应视重新检验结果，确定由哪方承担",true,{"key":23,"text":24,"correct":14},"D","因监理人未对隐蔽工程进行验收，应由监理人承担","2021\u002F2020教材P239页 监理人对质量有疑问的，可要求承包人对已覆盖的部位进行钻孔探测或揭开重新检验，承包人应遵照执行，并在检验后重新覆盖恢复原状。经检验证明工程质量符合合同要求的，由发包人承担货此增加的费用和（或）工期延误，并支付承包人合理利润；经检验证明工程质量不符合合同要求的，由此增加的费用和（或）工期延误由承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]