[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119652":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119652,789,1,"单选题","根据《标准施工招标文件》，承包人按照合同规定将隐蔽工程覆盖后，监理人又要求承包人对已覆盖部位揭开重新检验，经检验证明工程质量符合要求，由此增加的费用和延误的工期应由()承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",true,{"key":16,"text":17,"correct":18},"B","承包人",false,{"key":20,"text":21,"correct":18},"C","监理人",{"key":23,"text":24,"correct":18},"D","设计单位","2021\u002F2020教材P239页 覆盖工程隐蔽部位后，监理人对质量有疑问的，可要求承包人对已覆盖的部位进行钻孔探测或揭开重新检验，承包人应遵照执行，并在检验后重新覆盖恢复原状。经检验证明工程质量符合合同要求的，由发包人承担由此增加的费用和（或）工期延误，并支付承包人合理利润；",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]