[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119650":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119650,789,1,"单选题","根据《建设工程施工合同（示范文本）》（GF1999-0201）规定，承包人根据合同约定或监理人指示进行的现场材料试验，应由()提供试验场所、试验人员、试验设备器材以及其他必要的试验条件。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人",true,{"key":16,"text":17,"correct":18},"B","发包人",false,{"key":20,"text":21,"correct":18},"C","设计人",{"key":23,"text":24,"correct":18},"D","监理人","2021\u002F2020教材P239页 承包人根据合同约定或监理人指示进行的现场材料试验，应由承包人提供试验场所、试验人员、试验设备器材以及其他必要的试验条件。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]