[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119648":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119648,789,1,"单选题","根据《标准施工招标文件》中“通用合同条款”的规定，如承包人未通知监理人到场检查，私自将工程隐蔽部位覆盖的，对于监理人提出的重新检验要求，重新检验的费用()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","应由承包人承担",true,{"key":16,"text":17,"correct":18},"B","应由发包人承担",false,{"key":20,"text":21,"correct":18},"C","应视重新检验结果，确定由哪方承担",{"key":23,"text":24,"correct":18},"D","由承包人和发包人各承担50%","2021\u002F2020教材P239页 （4）承包人私自覆盖：承包人未通知监理人到场检查，私自将工程隐蔽部位覆盖的，监理人有权指示承包人钻孔探测或揭开检查，由此增加的费用和（或）工期延误由承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]