[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119647":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119647,789,1,"单选题","覆盖工程隐蔽部位后，监理人对质量有疑问的，可要求承包人对已覆盖的部位进行钻孔探测或揭开重新检验，承包人应遵照执行，并在检验后重新覆盖恢复原状。经检验证明工程质量不符合合同要求的，由此增加的费用和工期延误由()承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理人",false,{"key":16,"text":17,"correct":18},"B","承包人",true,{"key":20,"text":21,"correct":14},"C","发包人",{"key":23,"text":24,"correct":14},"D","分包人","2021\u002F2020教材P239页 （3）监理人重新检查承包人覆盖工程后，监理人对质量有疑问的，可要求承包人对已覆盖的部位进行钻孔探测和揭开重新检验，经检验证明工程质量符合合同要求的，由发包人承担由此增加的费用和工期延误，并支付承包人合理的利润。经检验证明工程质量不符合合同要求的，由此增加的费用和工期延误由承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]