[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119646":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119646,789,1,"单选题","根据《建设工程施工合同（示范文本）》（GF1999-0201）规定，由于发包人提供的材料或工程设备不合格造成的工程不合格，需要承包人采取措施补救的，发包人()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","不承担由此增加的费用和（或）工期延误",false,{"key":16,"text":17,"correct":14},"B","只承担由此增加的费用和（或）工期延误，不支付承包人合理利润",{"key":19,"text":20,"correct":14},"C","应承担由此增加的费用，但不顺延工期",{"key":22,"text":23,"correct":24},"D","应承担由此增加的费用和（或）工期延误，并支付承包人合理利润",true,"2021\u002F2020教材P239页 (2)由于发包人提供的材料或工程设备不合格造成的工程不合格，需要承包人采取措施补救的，发包人应承担由此增加的费用和（或）工期延误，并支付承包人合理利润。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]