[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119645":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119645,789,1,"单选题","某工程因施工需要，需取得出入施工场地的某条临时道路的通行权，根据《标准施工招标文件》中“通用合同条款”的规定，该通行权应当由()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人负责办理，并承担有关费用",false,{"key":16,"text":17,"correct":14},"B","承包人负责办理，发包人承担有关费用",{"key":19,"text":20,"correct":21},"C","发包人负责办理，并承担有关费用",true,{"key":23,"text":24,"correct":14},"D","发包人负责办理，承包人承担有关费用","2021\u002F2020教材P234页 除专用合同条款另有约定外，发包人应根据合同工程的施工需要，负责办理取得出人施工场地的专用和临时道路的通行权，以及取得为工程建设所需修建场外设施的权利，并承担有关费用。承包人应协助发包人办理上述手续。承包人只是协助。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]