[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119643":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119643,789,1,"单选题","根据《标准施工招标文件》，现场地质勘探资料、水文气象资料的准确性应由()负责。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","地质勘察单位",false,{"key":16,"text":17,"correct":18},"B","发包人",true,{"key":20,"text":21,"correct":14},"C","承包人",{"key":23,"text":24,"correct":14},"D","监理人","2021\u002F2020教材P234页 （6）发包人应将其持有的现场地质勘探资料、水文气象资料提供给承包人，并对其准确性负责。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]