[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119638":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119638,789,1,"单选题","由于承包人已完工程出现质量问题，监理人要求进行质量整改，导致暂停施工。如果承包人在收到监理人暂停施工指示后()天内不认真采取有效的复工措施，造成工期延误，可视为承包人违约。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","28",false,{"key":16,"text":17,"correct":14},"B","35",{"key":19,"text":20,"correct":14},"C","42",{"key":22,"text":23,"correct":24},"D","56",true,"2021\u002F2020教材P238页 由于承包人责任引起的暂停施工，如承包人在收到监理人暂停施工指示后56天内不认真采取有效的复工措施，造成工期延误，可视为承包人违约。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]