[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119636":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119636,789,1,"单选题","某工程项目施工过程中，由于恶劣的天气原因，工程师发出了暂停施工的指示。该指示发出56天后，工程师仍未发出复工指令，在这种情况下，承包人可以()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","立即自行复工",false,{"key":16,"text":17,"correct":14},"B","向监理人提交书面通知后自行复工",{"key":19,"text":20,"correct":14},"C","取消该工作",{"key":22,"text":23,"correct":24},"D","向监理人提交书面通知，要求监理人在收到书面通知后28天内准许已暂停施工的工程或其中一部分工程继续施工",true,"2021\u002F2020教材P238页 监理人发出暂停施工指示后56天内未向承包人发出复工通知，除了该项停工属于第12.1款（即由于承包人暂停施工的责任）的情况外，承包人可向监理人提交书面通知，要求监理人在收到书面通知后28天内准许已暂停施工的工程或其中一部分工程继续施工。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]