[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119633":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119633,789,1,"单选题","由于出现专用合同条款规定的异常恶劣气候的条件导致工期延误的，承包人有权要求发包人()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","延长工期",true,{"key":16,"text":17,"correct":18},"B","支付合理利润",false,{"key":20,"text":21,"correct":18},"C","支付违约金",{"key":23,"text":24,"correct":18},"D","增加费用","2021\u002F2020教材P237页 由于出现专用合同条款规定的异常恶劣气候的条件导致工期延误的，承包人有权要求发包人延长工期",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]