[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119632":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119632,789,1,"单选题","由于承包人原因，未能按合同进度计划完成工作，造成工期延误。对于该事件，下列说法中正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人应采取措施加快进度，并支付逾期竣工违约金",true,{"key":16,"text":17,"correct":18},"B","承包人应采取措施加快进度，并由发包人承担费用",false,{"key":20,"text":21,"correct":18},"C","监理人与承包人共同协商修订合同进度计划，并由发承担费用",{"key":23,"text":24,"correct":18},"D","承包人有权要求发包人延长工期","2021\u002F2020教材P237页 由于承包人原因，未能按合同进度计划完成工作，或监理人认为承包人施工进度不能满足合同工期要求的，承包人应采取措施加快进度，并承担加快进度所增加的费用。由于承包人原因造成工期延误，承包人应支付逾期竣工违约金。承包人支付逾期竣工违约金，不免除承包人完成工程及修补缺陷的义务。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]