[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119630":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119630,789,1,"单选题","根据《标准施工招标文件》中“通用合同条款”的规定，控制合同工程进度的依据是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人编制的施工进度计划",false,{"key":16,"text":17,"correct":14},"B","承包人的实际的工程进度",{"key":19,"text":20,"correct":21},"C","监理人批准的施工进度计划",true,{"key":23,"text":24,"correct":14},"D","承包人编制的分阶段计划","2021\u002F2020教材P236页 经监理人批准的施工进度计划称合同进度计划，是控制合同工程进度的依据。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]