[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119625":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119625,789,1,"单选题","监理人在发出开工通知前应获得（）同意，工期自监理人发出的开工通知中载明的开工日期起计算。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人",false,{"key":16,"text":17,"correct":18},"B","发包人",true,{"key":20,"text":21,"correct":14},"C","监理人",{"key":23,"text":24,"correct":14},"D","设计人","2021\u002F2020教材P236页 2.开工日期与工期监理人应在开工日期7天前向承包人发出开工通知。监理人在发出开工通知前应获得发包人的同意。工期自监理人发出的开工通知中载明的开工日期起计算.",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]