[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119624":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119624,789,1,"单选题","承包人应在接到开工通知后( )d内，向监理人提交承包人在施工场地的管理机构以及人员安排的报告。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","8",false,{"key":16,"text":17,"correct":14},"B","12",{"key":19,"text":20,"correct":14},"C","20",{"key":22,"text":23,"correct":24},"D","28",true,"2021\u002F2020教材P236页 （2）承包人应在接到开工通知28天内，向监理人提交承包人在施工场地的管理机构以及人员安排的报告，其内容应包括管理结构的设置、各主要岗位的技术和管理人员名单及资格，以及各工种技术工人的安排状况。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]