[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119623":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1119623,789,1,"单选题","某工程项目开工前，发包人向承包人提供了有关施工现场的地下管线资料，承包商按合同要求对管线予以了保护。由于发包人提供的资料不准确，导致承包人在正常施工过程中对地下管线造成了破坏，根据施工合同示范文本规定，对该情况的处理应是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","保护费用由发包人承担，事故损失由承包人承担",false,{"key":16,"text":17,"correct":18},"B","保护费用与事故损失均由发包人承担",true,{"key":20,"text":21,"correct":14},"C","保护费用由承包人承担，事故损失由发包人承担",{"key":23,"text":24,"correct":14},"D","保护费用与事故损失均由承包人承担","2021\u002F2020教材P235页 发包人应按专用合同条款约定向承包人提供施工场地，以及施工场地内地下管线和地下设施等有关资料，并保证资料的真实、准确、完整。因发包人提供的不准确，因此造成的费用应该发包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]