[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119617":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119617,789,1,"单选题","根据《标准施工招标文件》中“通用合同条款”的规定，项目参与各方中应对发包人提供的测量基准点、水准点及书面资料，以及施工场地内地下管线和地下设施的相关资料的真实性、准确性和完整性负责的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","承包人",false,{"key":16,"text":17,"correct":14},"B","监理人",{"key":19,"text":20,"correct":21},"C","发包人",true,{"key":23,"text":24,"correct":14},"D","有关勘测单位","2021\u002F2020教材P234页 发包人应在专用合同条款约定的期限内，通过监理人向承包人提测量基准点、基准线和水准点及其书面资料。发包人应对其提供的测量基准点、基准线和水准点及其书面资料的真实性、准确性和完整性负责。发包人提供上述基准资料错误导致承包人测量放线工作的返工或造成工程损失的，发包人应当承担由此增加的费用和（或）工期延误，并向承包人支付合理利润。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]