[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119616":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119616,789,1,"单选题","根据《标准施工招标文件》中“通用合同条款”的规定，除测量基准点、水准点及书面资料，以及施工场地内地下管线和地下设施的相关资料外，发包人还应向承包人提供()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","当地有关工程材料的市场信息资料",false,{"key":16,"text":17,"correct":14},"B","有关项目所在地的风俗习惯资料",{"key":19,"text":20,"correct":14},"C","有关项目所在地的法律法规资料",{"key":22,"text":23,"correct":24},"D","其持有的现场地质勘探资料、水文气象资料",true,"2021\u002F2020教材P234页 发包人应将其持有的现场地质勘探资料、水文气象资料提供给承包人，并对其准确性负责。但承包人应对其阅读上述有关资料后所作出的解释和推断负责。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]