[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119612":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1119612,789,1,"单选题","某建设工程项目以单价合同形式发包，在签订合同时根据估算的工程量和单价确定一个合同总价。工程完成后，实际完成的工程量乘以各项单价之和小于合同总价。根据单价合同的规定，工程款的支付应以()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","双方重新协商",false,{"key":16,"text":17,"correct":14},"B","实际完成的工程量乘以合同总价",{"key":19,"text":20,"correct":21},"C","实际完成的工程量乘以合同单价",true,{"key":23,"text":24,"correct":14},"D","实际完成的工程量乘以重新协商单价","2021\u002F2020教材P230页 对于单价合同，尽管是以实测工程量结算工程款，但投标人仍应根据图纸仔细核算丁程,当发现相差较大时，投标人应向招标人要求澄清。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]