[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119611":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1119611,789,1,"单选题","施工总承包管理模式在进度控制方面的特点有（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对施工总承包管理单位的招标不依赖于施工图设计，可以提前到初步设计阶段进行",true,{"key":16,"text":17,"correct":18},"B","设计、施工、供货之间的进度计划协调由施工总承包管理单位负责",false,{"key":20,"text":21,"correct":18},"C","项目总进度计划的编制由施工总承包管理单位负责",{"key":23,"text":24,"correct":18},"D","施工总承包管理模式对缩短建设周期不利","2021\u002F2020教材P226页 （二）施工总承包管理的特点2.进度控制对施工总承包单位的招标不依赖于完整的施工图设计，可以提前到初步设计阶段进行。而对分包单位的招标依据该部分工程的施工图，与施工总承包模式相比也可以提前，从而可以提前开工，缩短建设周期。施工总进度计划的编制、控制和协调由施工总承包管理单位负责，而项目总进度计划的编制、控制和协调，以及设计、施工、供货之间的进度计划协调由业主负责。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]