[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1119610":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1119610,789,1,"单选题","建设工程施工平行发包模式在进度控制方面的特点是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","需全部施工图完成后，才能进行招标，对进度控制不利",false,{"key":16,"text":17,"correct":14},"B","招标次数较少，对进度控制有利",{"key":19,"text":20,"correct":14},"C","无法做到边设计边施工.对进度控制不利",{"key":22,"text":23,"correct":24},"D","某部分施工图完成后即可开始这部分工程招标，有利于缩短建设周期",true,"2021\u002F2020教材P226页 (5)每完成一部分施工图设计，就可以进行该部分工程的施工招标，可以边设计边施工，可以提前开工，缩短建设周期，有利于进度控制。",{"id":6,"name":27,"category":28,"favorite":29},"二建建设工程施工管理","建筑工程",0]